Kaaboo Cayman
Festival Grounds Vertical Work
The construction of all vertical works at this site involved over 50 tradesmen, 6 managers and a wide variety of heavy equipment.
The broad scope of works for this project included unloading over 30 containers, erecting over 15,000 square feet of structures, as well as a wide variety of ancillary site works.
After successfully completing all construction over the course of several months leading up to the festival, our teams disassembled the entirety of our works and carefully re-packed all materials into containers for safekeeping until the following year.
Key Quantities & Scope of Work
Strict adherence to critical project deadlines for festival dates
Over 30,0000 man hours
Over 4,000 hours of Night Work
Over 15,000 square feet of Carbon Steel Structures
Hundreds-of-yards of concrete pouring and forming
Unloading, inventorying, inspecting, installing, removing and packing of over 30 containers of materials